Construction starts on segment three road upgrade



Work is shortly starting on segment 3 of the Big Ridge Rd upgrade and is expected to continue through to the end of May this year.

The upgrade work is required to allow safe access to the solar farm site for construction traffic later in the year.


The upgrade to segments 4 and 5 is continuing at the eastern end of Big Ridge Rd and should also be completed by the end of May. Work on the remaining segments including Barleyfields Rd is expected to commence in early April.


You can ask questions or provide feedback on the roadworks via our Facebook page or by calling Green Light Contractor’s Community Liaison Officer on 0417 261 453.


Construction milestone celebrated


The first ceremonial sod has been turned to mark the start of construction on the New England Solar Farm.


NSW Northern Tablelands MP Adam Marshall, Uralla Shire Deputy Mayor Councillor Isabel Strutt and UPC\AC Renewables CEO Anton Rohner came together to mark the occasion as a special ceremony at the entrance to the solar farm site.



More than three dozen workers are now on-site undertaking earthworks and road and drainage construction across nine kilometres of local roads before work can begin on the solar farm site.


The solar farm construction and road upgrades are being led by Green Light Contractors with the road design, survey and construction being undertaken by locally based businesses that have expanded their local workforce to support the project.


Other New England based surveying and engineering businesses have completed survey work for the site, as well as plans for the onsite operation and maintenance building.


Up to 700 jobs are expected to be created from the solar farm and battery project during peak construction and an additional 15 ongoing roles throughout the solar farm’s operational life.


UPC\AC CEO Anton Rohner said the project would continue to drive opportunities for local businesses, employment and help grow the local economy.


“The local community, our project landowners and civic leaders have been very supportive of the project over the past three years,” Mr Rohner said.


“We’re extremely excited to see construction start and the opportunities that are being returned and created for local business and workers.


“Once fully complete, the solar farm and battery project will be Australia’s largest hybrid solar and battery energy storage facility. It will play an important role in the energy transition already underway across the country.”


The New England Solar Farm and battery project will be built in two stages.


The first 400MW (AC) stage and the 33/330 kilovolt (kV) substation will be installed on the northern section of the site by Green Light Contractors.


While the first stage of the associated 400MWh battery project, a 50MW/1hour Battery Energy Storage System (BESS) capable of dispatching energy to the grid at times of high energy demand, will be constructed with the support of the NSW Government’s Emerging Energy Program.


The solar farm will connect with the existing 330kV transmission power line that crosses the site.


Once fully constructed, the project is expected to produce 1,800,000 megawatt hours (MWh) of clean, renewable electricity each year; enough to power more than 250,000 typical NSW homes.


We’re here to answer questions you have. 

 

Email: info@newenglandsolarfarm.com.au

Community Information Line: 1300 250 479

Facebook page: @newenglandsolarfarm

 

© 2018 UPC Renewables

Disclaimer and Privacy Policy

Subscribe for updates from the New England Solar Farm and Uralla Grants.